Guide · Capacity

Capacity planning in production: will the lines actually make what was promised?

Orders are accepted by sales and made by lines that have a fixed number of hours. Capacity planning is checking the two against each other before the week starts, not after an order is late.

Capacity planning in production compares the load that open orders put on each line, machine and team with the hours actually available, day by day, so bottlenecks are seen in advance and the plan can be changed while there is still time.

What you need

InputExample from a bakery
Firm demand by SKU and due dateSponge cake, cookies and rusk orders for the next two weeks
Line and machine ratesUnits or kilograms per hour on the cake line, ovens and packing
Working calendarShifts, holidays and planned maintenance per line
ManpowerOperators needed per line per shift, and who is available
PrioritiesWhich orders or channels go first when hours run short

How to do it, step by step

  1. Convert each order into hours on each line it passes through, using the standard rate.
  2. Fill each day’s hours in priority order: the most urgent due SKUs first.
  3. Use the hours left to pull ahead later orders, so lines are not idle.
  4. Add up load per machine and per team, and compare it with available hours.
  5. Flag anything above 100% as a bottleneck and anything above about 85% as tight.
  6. Change the plan, the shifts or the promise date before the day arrives.

Common mistakes

For movement of finished goods after the line, see the supply chain digital twin guide.

How Production & Procurement does it

Production & Procurement rebuilds the plant’s planning workbook as one live system. Firm orders, read from the plant’s own records, become a suggested plan: each working day, due SKUs take line capacity in priority order and pull-ahead fills the hours left. Planners can override any cell and freeze days already committed. The plan flows into a three-month projection, a raw-material plan net of stock and in-transit, a packaging plan from the packaging BOM, and a procurement list with what to order, how much and by when. Machine load and manpower are checked against the plan, red above 100% and amber above 85%. A digital twin of the site shows bins, lines and gates live, through the past month and seven days ahead, and says “not recorded” where data is missing. Every screen downloads to Excel, and plant systems are read, never written.

Questions

What is capacity planning in production?

Comparing the hours that open orders need on each line, machine and team with the hours available each day, so bottlenecks are found before orders are late.

How do I find the bottleneck in a production plan?

Add up the planned load per machine and team for each day and compare it with available hours; the first resource above 100% is the bottleneck. Packing is often the one missed.

What utilisation level should trigger a warning?

Many plants treat anything above 100% as a breach and above roughly 85% as tight; set the thresholds that suit your lines.

See it on your own data. Production & Procurement — Plan the line, buy on time. Book a 30-minute working session with an engineer.

General guidance, current as of the date above. Figures and examples are illustrative unless a source is linked.