Calculator

Raw material order-by date and days of cover calculator.

Enter stock, in-transit quantity, planned daily use and lead time to see how many days of cover you have, how soon you must order and how much.

Days of cover–
Order within–
Order quantity (kg)–

Runs in your browser; nothing is sent anywhere. Round the quantity to your supplier’s pack or truck size.

How it is calculated

Days of cover = (stock on hand + in transit) ÷ planned use per day. Order within = days of cover − supplier lead time − safety margin; at zero or below, order now. Order quantity = planned use per day × (lead time + safety margin + days the order should cover) − (stock on hand + in transit), never below zero. Count in-transit only if it arrives before stock runs out. Read raw material planning; to get the same three figures for every material from a live plan, see raw material planning from the production plan.

Worked example: when to order flour and how much

An illustrative bakery with round numbers, the same values the form opens with.

InputValue
Stock on hand12,000 kg
In transit, arriving before stock runs out4,000 kg
Planned use per day2,500 kg
Supplier lead time3 days
Safety margin1 day
Days the order should cover7 days
  1. Days of cover = (12,000 + 4,000) ÷ 2,500 = 6.4 days.
  2. Order within = 6.4 − 3 − 1 = 2.4, so the order must go out within 2 days.
  3. Order quantity = 2,500 × (3 + 1 + 7) − 16,000 = 27,500 − 16,000 = 11,500 kg.
  4. Round 11,500 kg up to the supplier’s pack or truck size (general guidance; the calculator does not round).

If the plan raises use to 3,200 kg a day, cover falls to 16,000 ÷ 3,200 = 5 days and the order must go out within 1 day: re-run the figures whenever the plan changes.

Questions

How do I calculate days of cover?

Days of cover is stock on hand plus in-transit quantity, divided by planned use per day. Count in-transit stock only if it arrives before the bin is empty. Illustrative example: 12,000 kg in stock and 4,000 kg in transit at 2,500 kg a day gives 6.4 days of cover.

When should I place a raw material order?

Place the order when days of cover minus supplier lead time and a safety margin reaches zero. Illustrative example: 6.4 days of cover, a 3-day lead time and a 1-day margin leave 2.4 days, so order within 2 days. At zero or below, the calculator shows Order now.

How much raw material should I order?

Order planned use per day times lead time, safety margin and the days the order should cover, minus stock on hand and in transit. Illustrative example: 2,500 kg × (3 + 1 + 7) days is 27,500 kg; less 16,000 kg already held, order 11,500 kg, rounded to the supplier’s pack or truck size.

See it on your own data. Production & Procurement — Plan the line, buy on time. Book a 30-minute working session with an engineer.

General guidance, current as of the date above. Figures and examples are illustrative unless a source is linked.