Guide · Materials
Raw material planning: turning the production plan into what to buy, and by when.
Most rush purchases happen because procurement learns what the plan needs after it is published. Raw material planning closes that gap.

Most rush purchases happen because procurement learns what the plan needs after it is published. Raw material planning closes that gap.
Raw material planning works out how much of each input the production plan will consume, subtracts what is already in stock or on the way, and turns the shortfall into purchase orders timed to the supplier’s lead time.
Worked example (illustrative): next week’s plan is 10,000 packs of cake at 0.25 kg of flour each, so gross need is 2,500 kg. With 900 kg in the silo and 600 kg in transit, net need is 1,000 kg. At 500 kg a day, the 1,500 kg on hand and on the way lasts three days. With a two-day lead time and one day of safety margin, the order has to go out today.
| Material | Driven by | Typical check |
|---|---|---|
| Flour | Bread, cake and cookie recipes | Silo level against daily use |
| Fat and sugar | Recipe quantity per batch | Days of cover against lead time |
| Wrappers and pouches | Packaging BOM per SKU | Print lead time is often the longest |
| Cartons | Packs per carton per SKU | Pack size and minimum order |
In manufacturing, MRP stands for material requirements planning: the method of exploding a production schedule through the bill of materials and netting it against stock, usually run inside an ERP. (On a retail pack, MRP means maximum retail price, which is unrelated.) Raw material planning is the job; MRP is one way of doing it.
| Raw material planning | MRP (material requirements planning) | |
|---|---|---|
| What it is | The planner’s job of making sure every input arrives before the line needs it | A calculation method, usually inside an ERP |
| Input | Production plan, recipes, stock, real supplier lead times | Master production schedule, bill of materials, inventory records |
| Output | A buy list with order-by dates, ranked by what stops a line first | Planned orders by date |
| Where it fails | When procurement sees the plan late | When BOMs, stock or lead times in the system are out of date |
Rank materials by what would stop a line first, not by value. A missing carton stops packing as surely as missing flour stops mixing.
Work out the date for one material with the raw material order-by date calculator, and check the plan fits the lines first with capacity planning in production.
Our production planning software, Production & Procurement, rebuilds the plant’s planning workbook as one live system. Firm orders, read from the plant’s own records, become a suggested plan: each working day, due SKUs take line capacity in priority order and pull-ahead fills the hours left. Planners can override any cell and freeze days already committed. The plan flows into a three-month projection, a raw-material plan net of stock and in-transit, a packaging plan from the packaging BOM, and a procurement list with what to order, how much and by when. Machine load and manpower are checked against the plan, red above 100% and amber above 85%. A digital twin of the site shows bins, lines and gates live, through the past month and seven days ahead, and says “not recorded” where data is missing. Every screen downloads to Excel, and plant systems are read, never written.
Multiply planned production by the quantity of each material per unit from the recipe or bill of materials, then subtract stock on hand and in transit to get net need.
Work out the day stock runs out at planned use, then subtract the real supplier lead time and a safety margin. That is the order-by date.
MRP stands for material requirements planning. It takes the production schedule, multiplies it through the bill of materials, subtracts stock on hand and on order, and produces planned purchase orders by date. In Indian retail, MRP also means maximum retail price; that has nothing to do with planning.
Yes. Wrappers, pouches and cartons come from the packaging BOM and often have longer lead times than the main ingredients.